|
I'm still trying to correct some of the problems on the site....please bear with me! |
|
|
MINUTES OF SPECIAL MEETING, RIALTO BOARD OF DIRECTORS
A&E Architects, P.C. will rely on these notes as the approved record of
matters discussed and conclusions reached PROJECT: Rialto Theater PROJECT NUMBER: 07007 MEETING LOCATION: Kohrs Library, Deer Lodge, MT MEETING DATE: 24 March 2008 MEETING SUBJECT: CD issues list resolution PREPARED BY: Nathan Blanding ATTENDING: Steve Owens, Gayle Mizner, Lee Jewell, Phil Maxwell, Ron Scharf,
Devin Wille, MEETING NOTES Issues List Reviewed:
1. Crawlspace- keep in under front lobby as drawn in DD package. 2. Tunnel- to be redrawn as pre-cast unit- minimum 5’ head clearance required. 3. Elevator- keep in drawings. Cab likely later addition. 4. Orchestra pit- foot print was confirmed. Depth to be increased to
accommodate future installation
1. Back stage addition- leave as single-story, add airlock vestibule as per DD drawing set. 2. Floor finishes- no changes to required to DD package. 3. Concessions area- this area was thought to be OK until after the meeting
in private discussion with 4. Front entry restoration- surgical removal of historic materials and
details will be required to repair Mezzanine level work: 1. Air handler platform will be added to the back stage area as per DD package. 2. Office floor will be raised to ensure ADA accessibility- window sill
height may be lower than 3. “Spider” window heights in stairwell may be at odd levels above stairs. It
was noted that those 4. Storage under balcony seats will be removed with new stadium truss strategy. Upper levels work: 1. Mech equipment in attic needs to be confirmed for weight, configuration
and fit. The sequencing of 2. The Rialto Board approved A&E’s proposal to draw in roof / attic
insulation at the bottom chord of 3. Suspended ceiling will be installed as planned, with the integration of
historic paint pattern panels 4. An electric winch is to be included for the maintenance of the central chandelier in the auditorium. 5. Provisions for incorporating theatrical lighting trusses into the ceiling
space as per the DD drawings General issues: 1. CD’s will continue to indicate a complete finish level for the entire
scope of work. Budgetary 2. Sound soak panels will be installed as per DD drawings. 3. Coordinated fabrics for wall panels, upholstery, curtains, were submitted for review and approved. 4. Lighting fixtures called out in DD cut sheet book were approved. Restored,
historic fixtures may be 5. Plumbing fixtures called out in DD cut sheet book were approved.
Value-engineering change 6. Door hardware from DD cut sheet book was identified as too expensive and
difficult to obtain. 7. Bath partition hardware and panels were approved. 8. Carpeting, tile, floor paint samples were approved, as were wall paint samples. 9. A&E will initiate contact with historic preservation firms capable of
making all necessary molds and 10. “New Construction Elements” and “Construction Sequencing” documents were
reviewed and 11. House, stage, lobby and work light controls need to be drawn out and
approved by Board prior to
(above-in grey) open space- current state
(above-in red) work platform- tbd... reusable materials
(above-in blue) insulation- spray at roof deck?
(above-in pink) duct work installed (above-in light orange) air handler installed... (above-in blue) insulation blow in at bottom chord?
(above-in orange) ceiling finished out
(above-in green) new bearing walls support attic floor
(above-in red) new beams support attic floor
(above-in blue) new stadium trusses installed
(above-in gray) interior finishing begins
basic shell- existing walls and columns
new beam lines
new center stadium truss
full stadium truss installation
duct work and mezzanine flooring
attic level and interior walls started |